Basic Installation Process of Curtain Wall Connectors
1. Pre-treatment: Clean the building structure surface and wall panel surface thoroughly, removing surface oil and dirt.
2. Measurement: Measure according to the drawings to confirm the connection positions and dimensions of the curtain wall.
3. Foundation Treatment: Install brackets and steel structures, ensuring the foundation of the curtain wall connection points is stable.
4. Bracket Fabrication: Fabricate connector brackets according to the drawings and actual conditions.
5. Connector Installation: Install the brackets and connectors to the curtain wall connection points.
6. Adjustment: Adjust according to the actual situation to ensure the connectors and curtain wall surface are aligned.
7. Fixing: Fix the connectors to the building structure using dedicated bolts and nuts.
8. Quality Inspection: Inspect the fixing performance and surface quality of the connectors and curtain wall.